Excel WORKDAY function

Adds working days to a date, skipping weekends and holidays. In Spanish Excel it is called DIA.LAB.

Syntax

English Excel

=WORKDAY(start_date, days, [holidays])

Spanish Excel (Mexico)

=DIA.LAB(fecha_inicial, días, [vacaciones])

Spanish Excel (Spain, Latin America)

=DIA.LAB(fecha_inicial; días; [vacaciones])

ArgumentWhat it is
start_dateThe starting date.
daysWorking days to add (negative to subtract).
holidaysoptionalA range with the holidays.

Example

WORKDAY(start, days, holidays) adds working days to a date, skipping Saturdays, Sundays and the holidays you list. It is how "delivery in 5 business days" is worked out.

=WORKDAY(B2,C2,$F$2:$F$3)

Common mistake

To count working days between two dates use NETWORKDAYS; WORKDAY calculates the end date.

About Ads

This site uses Google AdSense to display ads. These ads help us keep WebHerramientas completely free. Ads are managed by Google and meet strict security and privacy standards.

Advertising
Loading ad...

Ads help us keep WebHerramientas free for everyone

Practice WORKDAY

Type the formula in the sheet and check it instantly. Spanish or English function names both work. See all lessons

Delivery date with WORKDAY

WORKDAY(start, days, holidays) adds working days to a date, skipping Saturdays, Sundays and the holidays you list. It is how "delivery in 5 business days" is worked out.

Example=WORKDAY(B2,C2,$F$2:$F$3)DIA.LAB = WORKDAY

In D2, calculate the delivery date by adding the business days, skipping the holidays in F2:F3.

D2
ABCDEFG
1OrderDateBusiness daysDeliveryHolidays
2P-0111/12/2026511/16/2026
3P-0211/20/2026312/25/2026
4P-0312/21/20264
5P-0411/30/202610
6P-0511/13/20261
7

Tip: while typing, click a cell or drag across several to insert their reference.

Frequently asked questions

What is WORKDAY called in Spanish?
In Spanish Excel it is DIA.LAB. The formula =WORKDAY(B2,C2,$F$2:$F$3) is written =DIA.LAB(B2;C2;$F$2:$F$3) (or with commas in Mexico).
Why does WORKDAY use semicolons in some Excel versions?
It depends on regional settings. Where the comma is the decimal mark (Spain, much of South America), Excel separates arguments with semicolons. English Excel and Mexican Spanish Excel use commas.
What is the most common WORKDAY mistake?
To count working days between two dates use NETWORKDAYS; WORKDAY calculates the end date.